Give your water & sewer project a positive flow

Projects

Our proven experience.

Simply Water & Sewer understands the importance of a smooth project delivery in order to obtain the Section 73 Certificate as early in the project timeline as possible. Our experience, professionalism and systematic approach to all projects is essential in reaching this very clear objective.

Read about some of our recent projects:


Yellow Rock Road, Tullimbar

tullimbar.PNG

All the civil engineering design works for the 36 lot subdivision were undertaken by Simply Water & Sewer and LandTeam. The scope of works was to complete all civil engineering design which included sewer and water design, road design, storm water design and retaining wall design.

The scope of works entailed designing all the different underground services to ensure each block was served and having consideration of gravity connection points and avoiding clashes of any of the pipe infrastructure. The sewer design included lead-out work to connect to the end of the existing main in the front of a private property downstream of the site. The design process involved contacting the owners of this property and completing the Permission to Enter process both pre-development and post-construction.

The lead-in funding procurement process was undertaken through Sydney Water to facilitate the payment of the extra construction required to facilitate a connection to the development.

The potable water design had consideration of the future growth in the area. A 150mm main was extended along the frontage of the main road where future adjoining development will source their supply from.

The scope of works included the project management/supervision of the construction works for both the sewer and water infrastructure including tender management, preparation and monitoring of the ITP’s to ensure a quality product was delivered. All testing results were received and the process followed to achieve connection and hand over of both the sewer and water infrastructure to Sydney Water.


Darcy Road, Port Kembla

darcy rd.PNG

This was a staged development consisting of a 4 lot Torrens Title subdivision with construction of 8 units with future Torrens Title subdivision.

The overall scope of the development was considered up front to provide the developer with a scope of works that captured the intended result.

The design consisted of servicing the 8 future units for both sewer and water having consideration for compliance to the Building Plan Approval process including encasement requirements. The sewer servicing was achieved through the major works process and the water services were provided under the minor works process. This design also had consideration of all the other services on the site including stormwater drainage, gas, electricity and other site grading constraints.

The scope of this design was to set up all the future construction and subdivision requirements for servicing of sewer and water to provide value for money to the client and all works are completed whilst access to the site was available.

The scope of works also included the tender process, engagement of the contractor, supervision of the construction works and processing of claims from the contractor.




Jamberoo Road, Albion Park

jamberoo rd.PNG

All the civil engineering design works for the 17 lot subdivision were undertaken by Simply Water and Sewer and LandTeam. The scope of works was to complete all the civil engineering design which included sewer and water design, road design, stormwater design and retaining wall design.

The scope of works entailed designing all the different underground services to ensure each block was served and having consideration of gravity connection points and avoiding clashes of any of the pipe infrastructure. The sewer connection point was to a lead-out provided to the subject site which had to be extended on line and on grade to extend past the proposed interallotment drainage pipes and easement. Drainage limits of each site were also considered given to site grading constraints.

The potable water connection was to the end of an existing main through the recovery of a hydrant bend. The main fronted to proposed lots to minimise the number of road crossings and future maintenance and also provide value in design/construction to the developer.

The scope of works included the project management/supervision of the construction works for both the sewer and water infrastructure including tender management, preparation and monitoring of the ITP’s to ensure a quality product was delivered. All testing results were received and the process followed to achieve connection and hand over of both the sewer and water infrastructure to Sydney Water.



geetanjal-khanna-8CwoHpZe3qE-unsplash.jpg

Your project is in our hands

 

Testimonials


 
Thanks for doing such a great job managing the sewer and water install. The design and approval process was very timely and well documented. I also appreciate the efforts you made to organise and assess tenders and schedule a construction start within the time constraints. The construction process was smooth and you did a great job supervising the contractor and making sure the site was kept clean, tidy and safe. I am very happy with the quality of work undertaken.
— Steve R
 
 

 
 
Thank you for helping me with the Building Plan Approval process and water application which I needed for my Certifier.
— Michael R
 
 

 
 
I really do appreciate the customer focus and the prompt service you have provided to us. It is a great reflection on you. Great organisation, great personnel, outstanding customer focus.
— Danny B
 
 

 
 
Thank you so much for your support and guidance, you have been a pleasure to deal with. Again, thanks for being patient and so helpful in the whole water process.
— Philip M
 
 

 
 
I appreciate your help over the years with numerous inquiries, you have been a pleasure to deal with.
— Rose C
 
 

 
 

Contact us today to talk about how we can give your water and sewer project a positive flow.

SWS.PNG